West Ells SAGD Project
Click for Larger View

The West Ells region covers 9,856 contiguous gross and net hectares and is located within the Athabasca oil sands region between townships 94 to 96 and ranges 17 and 18 west of the fourth meridian.

A 10,000 bbl/day commercial SAGD application to construct the first phase at West Ells was submitted on March 31, 2010. The Company is expecting approval of the application in the near future.

The first phase of the West Ells SAGD project will proceed in two phases of 5,000 bbl/d each. Modular expansions will increase production in phases. According to our Management assumptions, West Ells is expected to be capable of producing up to 100,000 bbl/d of bitumen from the Wabiskaw zone over a period of 18 years with a productive life of over 50 years.

The West Ells area will be developed in phases to help control costs, implement improving technologies and capture efficiencies.

 

West Ells Timeline


Estimated First
Stream Completion
Expected Bitumen
Production (bbl/d)
West Ells A Phase 1 2013 5,000
West Ells A Phase 2 2014 5,000
West Ells A Phase 3 2017 20,000
West Ells B Phase 1
2020 20,000
West Ells B Phase 2
2023 20,000
West Ells C 2024 30,000


Total: 100,000